Highlights:
-
Slew of NOTAMs for Monday’s tentative launch of Starship Test Flight 11.
-
Last launch from Pad 1 as is. Conversion to Pad 2 style flame trench documents have been filed.
-
Catch hardware is coming off early, since booster 15 won’t be caught.
-
Booster 15 placed on launch mount.
-
Pad 2 progress, with last deluge tanks placed, and blast walls going up.
-
Big cranes being assembled for Gigabay work.
-
Massey’s test site repair and upgrade progress.
-
Florida construction progress, crane extensions
-
New Florida launch mount spotted
-
Falcon 9: Starlink 10-59, Starlink 11-17,
-
Blue Origin New Glenn booster moved to integration facility, targeting November launch.
-
Inversion Space Arc lifting body reveal, for military applications